Construction Zone

Date created: 9/27/04 Section: NEWS
  • Page 1 of 1
Capital improvement projects at Skyline College

Pacific Heights
start building 8 swing space construction Sept. 4
move building 8 classes to swing space Dec. 15, 2004 - Jan. 14, 2005

Improvements: track and soccer field
track area temporarily reopened Sept. 8, 2004 - March 1, 2005
track area closed for resurfacing March 1 - March 31, 2005
track and soccer field complete April 1, 2005

Field improvements: baseball and soccer
baseball field closed July 26 - Dec. 31
old softball field closed July 26 - Feb. 4, 2005

Improvements: tennis court
tennis court area closed July 26 - Dec. 31

Infrastructure: Field Maintenance Center
road closed to FMC from Loop Road June 29
construction complete Sept. 17

Infrastructure: other campus
parking lot 5
- cutover road and walkway
to Pacific Heights complete Sept. 17
- parking lot expansion to north
complete Sept. 17

parking lot 8 and 9
- Entrance from loop road Sept. 17
- Drainage inlets Oct. 15

Infrastructure: heating hot water loop
start construction October 2004
complete construction January 2005

Exterior painting
building 1 (in sections), portables 3A-3E,
track field house September 2004

Student Support and Community Services Center (building 6) and Science Annex (building 7A)
Loop road closed between
staff parking lot 6 and parking lot 5 Aug. 17
start construction September 2004

Seismic retrofit and modernization: building 3
building 3 closed September 2004
start construction October 2004
complete construction January 2006

Seismic retrofit and modernization: building 8
building 8 closed January 2005
start construction February 2005
complete construction January 2006
Page 1 of 1